1. Staircase and Lift wall to become constructed along with structure.
only two. Block work for common place and shafts are completed.
3. Power conduiting and box fixing is completed.
4. Staircase wall as well as ceiling plastering is completed.
5. Lobby area plastering is done.
6. Staircase railing and foyer railings are fixed.
7. Stairs and common area flooring as well as dadoing (as per specification) tend to be completed.
8. Granite coping as well as lift architraves granite works tend to be completed.
9. Putty, sanding as well as first coat paint to ceiling are completed.
10. Services such as Plumbing and fire are done.
11. Electrical wiring works tend to be completed.
12. Shaft door repairing is completed.
13. Shaft door painting is completed.
14. Grouting involving floor tile, wall tile as well as granite are done.
15. Silicon sealant is effective are completed.
16. Signages tend to be fixed.